The Residences at Mandarin Oriental, Boca Raton: Status, Litigation and Buyer's Guide (2026)
A factual guide to The Residences at Mandarin Oriental, Boca Raton, Penn-Florida's unfinished 12-story branded condo tower at 105 East Camino Real in Via Mizner: what was planned, the 2019 and 2023 condo loans, the December 2025 hotel bankruptcy, the July 2026 condo foreclosure suit, buyer deposit lawsuits, MLS records and what contract holders and prospective buyers should check.
View the The Residences at Mandarin Oriental, Boca Raton building page

Join the The Residences at Mandarin Oriental, Boca Raton Waitlist
Get early-bird pricing and exclusive updates on this development
The Residences at Mandarin Oriental, Boca Raton: Status, Litigation and Buyer's Guide (2026)
The Residences at Mandarin Oriental, Boca Raton is a 12-story branded condominium tower at 105 East Camino Real in downtown Boca Raton, part of Penn-Florida Companies' Via Mizner development at the corner of Camino Real and Federal Highway (US 1). It was announced in November 2015 alongside a 164-room Mandarin Oriental hotel next door, with SB Architects designing both buildings and a sky bridge linking them. Construction began in 2019. As of October 23, 2026, neither the condo tower nor the hotel is finished, and no current delivery date has been published.
This is not a typical pre-construction guide. The project has been delayed for years, the hotel entity filed for Chapter 11 bankruptcy in December 2025, and in July 2026 the condo tower's lenders filed a $417.7 million foreclosure suit. More than a dozen buyers have sued over missed delivery deadlines. This guide sets out what was planned, what has been reported in court filings and the press, what MLS records show and what contract holders and prospective buyers should verify. It is not legal advice; anyone with a contract or deposit should work with a Florida real estate attorney.
At a glance
| Detail | Information |
|---|---|
| Name | The Residences at Mandarin Oriental, Boca Raton |
| Address | 105 E Camino Real, Boca Raton, FL 33432 |
| Neighborhood | Downtown Boca Raton, Via Mizner |
| Developer | Penn-Florida Companies (condo owner entity: Via Mizner Owner III LLC) |
| Architect | SB Architects (hotel and residences) |
| Height | 12 stories |
| Residences | Reported as 85 to 92 since 2019, depending on the source (100 in the 2015 announcement) |
| Hotel next door | Mandarin Oriental, 164 rooms, 103 E Camino Real (separate owner entity) |
| Construction start | 2019 |
| Construction financing | $225 million from Madison Realty Capital (2019); condo tower mortgage of $270 million secured in August 2023 |
| Original completion target | Late 2017 (2015 announcement) |
| Delivery date | None currently published; a developer status report to the city, reported in June 2026, targeted the fourth quarter of 2026, but the contractor says it stopped work before May 2026 |
| Status (October 23, 2026) | Unfinished and stalled; foreclosure suit filed July 2026; buyer litigation ongoing |
Sources: Penn-Florida's November 2015 announcement, REBusinessOnline's and Connect CRE's July 2019 loan reports, The Coastal Star's 2019, 2025 and 2026 reports, Discover South Florida's 2026 coverage of the bankruptcy and The Real Deal's 2026 reports.
What was planned
When Penn-Florida and Mandarin Oriental announced the project in November 2015, the plan called for 100 condominiums in a tower adjoining the hotel, with layouts from one to four bedrooms, a sky bridge to the hotel and a late-2017 opening. Douglas Elliman was named the exclusive sales agent. The hotel program included a rooftop restaurant and bar, a lobby lounge, a club lounge, a 4,500-square-foot ballroom, a spa, a fitness center and a rooftop pool.
The residence count changed as the design evolved. Connect CRE's report on the 2019 construction loan cited 92 units, Discover South Florida's 2026 coverage cites 88, and The Real Deal's May 2026 coverage refers to 85 branded residences. Ask any seller which count the current condominium declaration uses.
The Via Mizner plan also included the 366-unit 101 Via Mizner rental building, which Cardone Real Estate Acquisitions bought for a reported $235 million in 2025, the 60,000-square-foot Shoppes at Via Mizner and, in the 2015 announcement, a private club with social, fitness and golf amenities. REBusinessOnline's 2019 report described the hotel and condo tower as joined by an upper-level bridge and an underground parking tunnel.
Residences and sizes in MLS records
Penn-Florida has not published a current floor-plan catalog. Seven residences appear in MLS listing data (checked October 23, 2026), and they give a sense of the sizes sold:
| Residence | Bedrooms | Size | List price |
|---|---|---|---|
| 811 | Two | 2,273 sq ft | $4.5 million |
| 707 | Two (listing remarks describe a three-bedroom corner plan) | 2,579 sq ft | $3.2 million |
| 502 | Three | 2,771 sq ft | $4.5 million |
| 506 and 606 | Four | 4,190 sq ft | $5.1 million and $5.6 million |
| 501 | Four | 4,693 sq ft | $6.6 million |
| Penthouse 09 | Five | 6,253 sq ft | $15.5 million |
These are MLS listing figures, not sale prices. All seven are recorded as pending or under contract, were first listed between April 2022 and July 2023, and none has closed. They are pre-construction contracts that have stayed open on the MLS while the building remains unfinished, not current offerings. In July 2019, when the condo construction loan closed, The Coastal Star reported pricing starting at $2 million.
Listing remarks describe ocean and golf course views. The listings carried projected association fees of about $3,400 to $6,300 a month; those projections date from the 2022 and 2023 listings and should not be relied on.
Location: Via Mizner and Camino Real
The site is at the southern edge of downtown Boca Raton, at Camino Real and Federal Highway. Camino Real runs east to the Intracoastal Waterway and The Boca Raton resort. Royal Palm Place is a short walk north and Mizner Park a short drive, with the beach across the Intracoastal. For the wider market, see our Boca Raton guide.
Photos are drawn from MLS listing photography for the building and may show renderings or earlier construction stages.
Timeline: financing, delays and litigation
| Date | Event |
|---|---|
| November 2015 | Hotel and 100-residence tower announced; late-2017 completion target |
| 2019 | Construction begins; Madison Realty Capital provides a $225 million construction loan for the condo tower (July 2019) |
| 2022 | Most buyer contracts signed, according to The Coastal Star |
| August 2023 | Lenders' $270 million mortgage on the condo tower is secured, according to the foreclosure complaint as reported by The Coastal Star |
| June 2024 | Interest payments on the condo loan stop, according to the lenders' complaint |
| Summer 2024 | First group of buyers sue to recover deposits |
| September 2025 | Condo loan matures and is not repaid, according to the lenders' complaint |
| December 23, 2025 | Hotel entities Via Mizner Owner II and Via Mizner Pledgor II file Chapter 11 (about $210 million in secured claims) |
| Before May 6, 2026 | Contractor Strategic Group Builders stops work on the condo site, per its July 6, 2026 lien-foreclosure complaint seeking $24.1 million |
| June 2026 | Bankruptcy judge approves a June 22 hotel auction date; The Coastal Star reports the developer's city status report targeting condo completion in the fourth quarter of 2026 and the hotel in the third quarter of 2027 |
| June 2026 | One buyer couple settles for $2.1 million plus interest; on June 29 a judge rules another couple can demand their $1.98 million deposit from the title companies holding it |
| July 7, 2026 | Hotel auction postponed to August 14, with a sale hearing set for August 21 |
| July 17, 2026 | Lender group files a $417.7 million foreclosure suit against Via Mizner Owner III |
| August 2026 | Penn-Florida affiliates sue a Madison Realty Capital affiliate in New York; a judge temporarily blocks a scheduled UCC foreclosure auction and sets a hearing for October 1 |
The hotel bankruptcy
The Chapter 11 case covers only the hotel: Via Mizner Owner II and Via Mizner Pledgor II filed on December 23, 2025, in the U.S. Bankruptcy Court for the Southern District of Florida. Reports put the senior claim of TIG Romspen, the hotel's senior lender, at about $130.2 million, a second secured claim from Via Mizner Funding at about $80 million and unsecured claims at about $24.6 million, including a disputed claim from Mandarin Oriental of about $502,600. Penn-Florida valued the completed hotel at more than $450 million. A June 22, 2026 auction was approved, then postponed to August 14, with TIG Romspen able to credit-bid. We have not found a public report of the auction's result or a court-approved sale as of October 23, 2026.
The condo foreclosure
The condo tower is owned by a different affiliate, Via Mizner Owner III, and is not part of the bankruptcy. On July 17, 2026, Via Mizner Lender 1 LLC, as agent for a lender group, filed a foreclosure complaint in Palm Beach County Circuit Court seeking $417.7 million: the original $270 million loan plus interest, advances and fees. According to The Coastal Star, the complaint says interest payments stopped in June 2024 and the full payoff due in September 2025 was missed, and it seeks to cut off the claims of what it calls purported junior lienholders, including Strategic Group, and purported contract purchasers. In August 2026 Penn-Florida's affiliates sued a Madison Realty Capital affiliate in New York, seeking more than $500 million; Madison was the condo tower's original construction lender. A judge temporarily blocked a separate UCC foreclosure auction pending an October 1 hearing. We have not found a reported outcome of that hearing as of October 23, 2026.
Buyer lawsuits and deposits
According to The Coastal Star's June and July 2026 reports, more than a dozen buyers have sued Via Mizner Owner III, in a first wave mostly in summer 2024 and a second from late 2025 through spring 2026. Most contracts were signed in 2022, and buyers argue that the contracts' delivery deadlines passed in 2025; Penn-Florida's attorney argues the completion date was an estimate and cites COVID-19, supply-chain problems, inflation, contractor price increases and Hurricanes Ian and Nicole in 2022. Reported outcomes include a June 29, 2026 ruling that lets one couple demand their $1.98 million deposit from the title companies holding it (the developer moved for rehearing), a $2.1 million settlement plus interest for another couple, who had placed a $1.65 million deposit, and eight confidential settlements. Plaintiffs reported deposits of roughly $1 million to $2 million each.
Florida law lets a developer use deposits above 10 percent of the price for construction if the contract allows it, so part of a buyer's deposit may no longer be in escrow. How any individual deposit is treated depends on the contract, the escrow agent and the courts.
Is the Mandarin Oriental brand still attached?
As of October 2026, Mandarin Oriental's website still has a Boca Raton page in its upcoming residences section, and MLS listings still carry the name. The brand licenses its name and is not the developer. A court-ordered sale or foreclosure could bring in a new owner, and whether the brand stays would depend on the agreements then in force. We have not found a public statement from Mandarin Oriental on the status of the Boca Raton agreements. Anyone buying on the strength of the brand should ask for written confirmation of the current residential license and hotel management agreement.
How it compares nearby
| Building | Address | Residences | Status (October 2026) |
|---|---|---|---|
| The Residences at Mandarin Oriental | 105 E Camino Real | 85 to 92, by report | Unfinished and stalled; foreclosure and buyer litigation |
| Royal Palm Residences | 475 E Royal Palm Rd | 48 | Completed 2024 |
| ALINA Residences | 200 to 220 SE Mizner Blvd | About 303 | Completed in phases |
| Glass House Boca Raton | 280 E Palmetto Park Rd | 28 | Under construction; late-2027 target |
| Mandarin Oriental Residences, West Palm Beach | 5400 N Flagler Dr, West Palm Beach | 87 | Pre-construction; Great Gulf, targeted 2031 |
Buyers drawn to a new downtown Boca Raton address have finished alternatives, such as Royal Palm Residences and ALINA, where the building, budget and association can be inspected. Buyers specifically after Mandarin Oriental branding can look at Mandarin Oriental Residences, West Palm Beach, a standalone 31-story tower by Great Gulf that is a separate project from Boca Raton.
What to check before you act
- If you hold a contract, have a Florida real estate attorney review the delivery and outside-completion terms, the escrow agreement and whether any part of your deposit was released for construction. The foreclosure complaint seeks to cut off the claims of contract purchasers, so check whether you have been named or served.
- Confirm who controls the property. Search the Palm Beach County Clerk's records for the foreclosure case and any judgment, and the bankruptcy docket for the hotel case, before relying on any timeline.
- Get the brand status in writing. Ask for evidence that the residential license and hotel management agreement remain in force.
- Treat MLS listings as historical. The seven pending listings date from 2022 and 2023; any assignment or resale would need the current owner's and lender's cooperation.
- Verify the condominium documents. Residence counts, amenities and fees have changed since 2015; rely only on the current recorded declaration and budget.
- Compare finished buildings. Our Boca Raton guide and the pre-construction section list alternatives, and our guide to buying pre-construction explains deposit protections in general.
Frequently Asked Questions
Where is The Residences at Mandarin Oriental, Boca Raton?
At 105 East Camino Real in downtown Boca Raton, FL 33432, within Penn-Florida's Via Mizner development at Camino Real and Federal Highway. The hotel is next door at 103 East Camino Real.
Is the Mandarin Oriental Boca Raton condo finished?
No. As of October 23, 2026 the 12-story tower is unfinished and there is no current published delivery date. A mid-2026 city status report targeted substantial completion in the fourth quarter of 2026, but the contractor, Strategic Group Builders, reported stopping work before May 2026, the lenders filed for foreclosure in July 2026 and we have found no report that work has resumed.
Did the Mandarin Oriental Boca Raton go bankrupt?
The hotel entities, Via Mizner Owner II and Via Mizner Pledgor II, filed Chapter 11 on December 23, 2025. The condo tower's owner, Via Mizner Owner III, was not part of that filing; it faces a $417.7 million foreclosure suit filed July 17, 2026.
What happened at the auction?
The hotel auction set for June 22, 2026 was postponed to August 14, 2026. A separate UCC auction tied to the condo developer was temporarily blocked by a New York judge in August 2026. We have not found a reported result for either as of October 23, 2026.
What happens to buyer deposits?
It depends on each contract and escrow arrangement. In June 2026 one buyer couple settled for $2.1 million plus interest, and a judge ruled that another couple could demand their $1.98 million deposit from the title companies holding it; eight others settled confidentially. Deposit holders should get legal advice.
How many residences does it have?
The 2015 plan called for 100. Later reports cite between 85 and 92, with The Real Deal's 2026 coverage citing 85 and Discover South Florida's citing 88.
Follow this building
Visit the building page for MLS records and updates. Contact REHUB to compare finished Boca Raton condos with the remaining pre-construction options.
Condo buildings in Boca Raton
Photos, floor plans, amenities, and current units for sale and rent in each.
- ALINA Residences Boca Raton
- Boca Beach House
- Glass House Boca Raton
- Manatee Pointe at Lago Mar
- Royal Palm Residences
- The Residences at Mandarin Oriental, Boca Raton
- The Residences at The Boca Raton
- Tower 155
Tags
Born and raised in Miami, Kyle Benjamin combines a background at Blackstone and Oppenheimer & Co. with hands-on coding and financial analysis. He founded REHUB Miami to make South Florida real estate easier to research through building comparisons, market data, floor plans, and local insights.
Read Kyle’s full bioRelated Articles
Glass House Boca Raton: 28-Residence Downtown Condo on Palmetto Park Road, Buyer's Guide (2026)
A buyer's guide to Glass House Boca Raton, the 28-residence glass condominium under construction at 280 East Palmetto Park Road downtown: two- to four-bedroom homes of about 2,500 to 3,865 square feet, a rooftop pool level, pricing from $2.7 million, the $70 million construction loan, MLS asking prices and a late-2027 completion target.

ATMA Miami by Aman: Brickell's 1,049-Foot Wellness Tower Pre-Construction Guide (2026)
A buyer's guide to ATMA Miami by Aman, the 1,049-foot condominium, hotel and members' club tower planned at 1111 Brickell Bay Drive: the OKO Group and Oak Row Equities site, SHoP Architects' design, the one- to six-bedroom residence program, the 120,000-square-foot wellness center developed with Novak Djokovic, the 2031 completion estimate, what has not been published yet and how to prepare for the sales launch.

Armani/Casa Residences Pompano Beach: Pre-Construction Condo Guide (2026)
A buyer's guide to Armani/Casa Residences Pompano Beach, the planned pair of 19-story towers at 1550 N Ocean Blvd with 28 full-floor residences: the developer team, G3 Architecture's design, Armani/Casa interiors, West 8's park, amenities, parking, the $5 million launch price from November 2024, where the project stands and how it differs from Residences by Armani Casa in Sunny Isles Beach.